On this page
Tap positions for comparison with factory results
Include the unit serial number, site designation and required commissioning measurements. If results are to be compared with factory readings, supply the original tap positions and recorded temperature alongside them. List any separate request to calibrate the instruments used for testing.
If two visits report different winding ratios, compare the tap designations before treating the difference as drift. A ratio shift between adjacent taps can be entirely intentional. Record the selected tap and winding pair against each comparison result.
Specifications and service checks
If maintenance is investigating a voltage drop that appears only under load, a no-load ratio check answers just one part of the question. Include the tap setting, load condition and which terminal voltage changed when specifying the service.
- Range and configuration
- Rated kVA or MVA describes power capacity. Ratio, winding resistance, losses and insulation characteristics are separate test quantities.
- Manufacturers and models
- Hitachi Energy supplies transformer families with different ratings, vector groups and arrangements of taps. Use the nameplate to define the individual unit.
- What we check
- Identify the electrical tests required for the unit and report each on its own terms, such as turns ratio at stated taps or winding resistance corrected to temperature.
- Reference equipment and accuracy
- Use calibrated ratio and resistance instruments or a suitable power measurement system, according to the required test. Include temperature measurement where corrections are applied.
- When to repeat the check
- Plan testing around commissioning, changes in condition, faults or maintenance and the asset owner's inspection programme.
Technical references Ground-mounted distribution transformers