On this page
Resistance ranges and connection method
Provide the working resistance values, selected ranges and connection method. Include the state of any relative-zero setting. If a temperature sensor is being measured in ohms, keep the raw resistance comparison separate from a later conversion to temperature.
A resistance standard connected with short, clean leads may give a stable check while the production component reads differently on another range. Record the selected range and test signal before assuming that the difference originates in the standard or the meter.
Specifications and service checks
A low-range two-wire meter that reads 0.3 Ω with its leads shorted already includes the lead and contact contribution. State whether the working procedure uses relative zero or subtracts a lead reading before comparing a low-resistance part.
- Range and configuration
- A displayed resistance is reported in ohms. A continuity alarm instead changes state near a threshold and may have a separate response-time requirement.
- Manufacturers and models
- Fluke 87V is an example with distinct resistance and audible-continuity functions. Record which indication is used to release the item under test.
- What we check
- Compare the resistance ranges with known values. For a continuity tester establish the resistance at which its alarm operates and releases, using the required test current.
- Reference equipment and accuracy
- Use calibrated resistors or a resistance box covering the threshold. For low values, account for lead and contact resistance.
- When to repeat the check
- Verify after replacing test leads and track changes in the resistance limit that operates the alarm.
Technical references Fluke 87V Industrial Multimeter
Resistance meter
At low resistance, the resistance of the leads may be comparable with the part under test. Towards the higher end of the instrument’s range, leakage through insulation and the time needed for a reading to settle can matter more. Give us the resistance values you actually measure.
Give the working resistance intervals and two- or four-terminal configuration. Copy the test-current setting if it is selectable. Where the instrument has a relative or zero function, note whether it is applied before the production measurement.
One bench may record the resistance of a cable including its connectors, while another measures conductor resistance between sense contacts. If those reports disagree, establish the boundaries of the measurement before applying the difference as a correction to the meter.
A resistor network may be checked in circuit on one bench and as an isolated component on another. Parallel paths can lower the in-circuit reading. Identify how the part is connected if the request arises from a disagreement between two inspection steps.
- Range and configuration
- State whether the work is at milliohms, ordinary ohms or high resistance. A four-wire low-resistance measurement addresses lead drop; guarded connections may be needed for very high values.